Phase 2 membrane project, Day 8–July 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 22°C, mix of clouds and sun
Workers onsite: At least four

Work done today:

  • Further work on preparing the concrete slab in front of Building 244 for new membrane.
  • Sealant, membrane, and aeration (drainage) mats have arrived for the area.